Question set 02 When compared to engineering/construction projects, IT projects have the following characteristics: · It is harder to predict source of change · Change requests are more frequent · During testing, it is difficult to test all possible scenarios Unified Process framework is suitable for projects where: · Requirements are clearly defined upfront · Critical infrastructure is being delivered · There is emphasis on people, i.e., self-organized flexible teams Unified Process framework is: · Incremental · Iterative · Agile Unified Process framework is: · user story driven · use case driven · business process driven The correct sequence of activities within UP lifecycle is: · Business modeling, Requirements, Analysis, Design, Implementation, Testing, Deployment · Requirements, Analysis, Business modeling, Design, Implementation, Testing, Deployment · Requirements, Analysis, Design, Testing, Implementation, Deployment, Business modeling The correct order of phases within UP lifecycle is: · Inception, Elaboration, Construction, Transition · Inception, Elaboration, Implementation, Transition · Elaboration, Inception, Implementation, Transition In which phase of the UP lifecycle there is the highest amount of testing: · Elaboration · Construction · Transition In which phase of the UP lifecycle there is the highest amount of analytical work: · Inception · Elaboration · Construction In which phase of the UP lifecycle there is the highest amount of design work: · Inception · Elaboration · Construction In which phase of the UP lifecycle there is the highest amount of writing code: · Elaboration · Construction · Transition Which of the following diagrams are used within Unified Process Framework during the analysis phase: · Use case diagram · Entity-relationship diagram (ERD) · Sequence diagram Which of the following diagrams are used within Unified Process Framework during the requirement collection phase: · Use case diagram · Class diagram · Sequence diagram